+61 3 9369 6200
Our Partner:
Click Here
Major Projects
Gas pipeline
Contractual requirements for surety of gas supply in remote Western Australia read more
Gas plant
Contractual requirements for the supply of Ethane resulted in the requirement read more
Anzon Petroleum
Victoria's first FPSO required the fitout of an existing ship with processing equipment. read more
Chemical injection
Whilst AFH have enjoyed the opportunity to provide a range of chemical injection read more
Rotor-Tech
Many gas producing fields require water removal to produce pipeline specification gas read more
Pump / Reactor
The need for a custom built solution arose for a full scale Biodiesel production read more
Mechanical seal
As a supplier of mechanical seal support systems to mechanical seal suppliers to the Oil read more
Salt removal
A gas plant in Western Victoria required the use of a salt removal system read more
Sundyne pump
AFH's first foray into the supply of a significant engineered skid package read more
Cooling water
It seems that most projects require customized packages for a variety of reasons. read more
Reciprocating
Neuman & Esser South East Asia (NEASEA) were awarded the supply read more
News
AFH are appointed
AFH are appointed as the exclusive... read more
Nikkiso purchases Lewa
Nikkiso purchases Lewa read more
AFH distributed product
AFH distributed product for... read more
LAS supplies
LAS supplies a fully integrated Fuel... read more
Salt removal package
A gas plant in Western Victoria required the use of a salt removal system as part of its' Mono Ethylene Glycol (MEG) regeneration system.
You are Here : Home  >> Salt removal package


Revolutionary thinking settled on the use of Electrodialysis as the primary process for this application but local packaging of the ancillary equipment was needed to ensure maximum compliance to the project specifications as well as cost effective logistical movement of the equipment to site.

This is the first package that AFH have engineered that involved a PVC piped system that utilized high bond strength and chemically resistant glue. The total system was painstakingly assembled over 5 modular skids in total to allow the complete package to be transported to site using low load road rigs.

Salt removal package


In addition to the Electrodialysis stack, the package included PolyPropylene tanks, centrifugal and metering pumps, calibration vessels, valving, control instrumentation and a water chiller system.

After transport to site and mounting on location, AFH staff were engaged for all of the site based connections, including manufacture and assembly of the site based PVC pipe systems.